The Government in G.O.Ms.No:40, PD&SI Department, dt 04.03.2016 has established the State Level Technical Cell for the Hill Areas of Tamil Nadu (STCHA) at the State Level and hosted in the SPC under TNSLURB for administration and field implementation of the SADP.
SCOPE OF SADP SCHEME
Special Area Development Programme targets the hilly areas of 11 Districts
SADP WORKS IMPLEMENTED THROUGH FOLLOWING DEPARTMENTS
YEARWISE BUDGET GRANT ALLOTED
RE 2016-17 : Rs. 25.00 Crore
BE 2017-18 : Rs. 75.00 Crore
BE 2018-19 : Rs. 75.00 Crore
For year 2019-20, Budget Grant of Rs. 75.00 Crore have been allotted
FINANCIAL SANCTION ACCORDED
In the year 2016 -2017, 552 projects were approved in SLEC – I at on outlay of Rs.56.86 Crore (308 project at a cost of Rs.32.10 Crore for unit - I & 244 project at a cost of Rs.24.75 Crore for Unit – II) Administrate sanction have been accorded for all project and Financial Sanction was accorded and funds were released for Rs.25.00 Crore.
In the year 2017 – 2018, 404 projects were approved in SLEC – II at on outlay of Rs.75.61 Crore (231 projects at Rs.33.12 Crore for unit I and 173 Projects at Rs.42.49 Crore for Unit II). Administrative Sanction was accorded to 352 projects for Rs.55.32 Crore (208 projects at Rs.27.89 crore for unit I and 144 Projects at Rs.27.43 for Unit II) and Financial Sanction was accorded and funds were released for Rs.75.00 Crore including remaining projects in 2016-17 and 2nd installment for previous year projects. 52 project were dropped due to want of funds.
In the year 2018-19, 606 projects were approved in SLEC III,IV and V at a cost of Rs. 84.69 Crore ( 330 Projects at Rs 45.39 Crore for Unit –I and 276 Projects at Rs 39.30 Crore for Unit II). Administrative Sanction have been accorded for 605 projects at a cost of Rs. 84.52 Crore ( 330 Projects at Rs 45.39 Crore for Unit –I and 275 Projects at Rs 39.12 Crore for Unit II). and Financial Sanction was accorded and funds were released for Rs.75.00 Crore including remaining projects in 2017-18 and 2nd installment for previous year projects. 1 project was dropped due to non receipt of justification.